Important Notice: We've been notified by the community association of a pool closure for an important re-plastering project. According to the Contractor, the project will take approximately 7 weeks from the April 14th start date, including curing, pool water balancing; to complete with a tentative reopening of June 10. Weather and unforeseen circumstances will have an impact on the target completion date.
The work involves various phases, which may be noisy and intrusive on guest experience and enjoyment. The first two weeks will be the most intrusive part of the project. Please reach out to our office for any questions or concerns.
We appreciate your understanding during this time and remain committed to ensuring you have a pleasant stay!